Before you can add line items in the SOV Workbench, you must define at least one SOV section for the job. Without an SOV section, the system displays error SV559: Cannot add Item: SOV structure has not been defined.
Add an SOV section
Open the job in COINS and go to the SOV Workbench.
This can be found here: Job Contract Manager > SLR > SOV* Workbench
In the small tree menu on the left, click SOV.
Select Add.
Complete the required fields to define your SOV section.
Click Save to confirm.
đNote: Once the SOV section is saved, return to the SOV Workbench to add your line items as normal.
If you are setting up a single line item SOV, you only need to add one section. The contract value should already reflect correctly from any prior budget upload.