Development Re-Plans in Coins ERP+

Written by Denisa Arjoca
Updated over 2 weeks ago

If you change the lots you plan to build on a development (for example, not building certain lots, building additional lots, or replacing lots with different templates), this has various implications for different functions in Coins ERP+.

The table below explains these.

Module *

Function

Lots Deleted

Existing Template on Site

New Template on Site

Existing Template on Site

New Template on Site

schedule of values

Bills

All bill items for the deleted lots will be deleted automatically.

Apply existing site template bill to new lots.

Create new site template bills and apply to new lots.

Run the lot rebuild option for the changed lots.

Create new template bills and run the lot rebuild option for the changed lots.

Create Orders

Lots cannot be deleted if orders have been created for them. **

For materials: you can add new lots as a change order to an existing order.

For subcontracts: New lots will create new orders - not change orders to previous orders.

Coins ERP+ will prompt user with change order required and these can be automatically created.

House Sales

Sales Workbench

A lot cannot be deleted if any events have been recorded (but the events can be deleted first if required). **

Input all information for new lots as normal.

Input any amendments to sales information as normal.

Sales and Construction Forecast

Forecast for deleted lots will be automatically deleted.

Input forecast dates and prices for new lots as normal.

Input any amendments to forecast dates and prices for changed lots as normal.

VAP

Matrix Orders

A lot cannot be deleted if it is included in any matrix subcontract. **

New lots can be added to existing matrix subcontracts provided these were not created from BQ subcontract orders.

If the order was created from BQ it will be automatically changed; otherwise will need to be updated by manual input.

Budgets

Budget for deleted lots will be automatically deleted.

Either run the option to update budgets from BQ for changed lots, or rebuild lots from templates.

Either run the option to update budgets from BQ for changed lots, or create new template budgets and then rebuild the lots from templates.

Either run the option to update budgets from BQ for changed lots or rebuild lots from templates.

Either run the option to update budgets from BQ for changed lots, or create new template budgets and then rebuild the lots from templates.

check Sheet Valuation

A lot cannot be deleted if any checks have been input for it. **

Input all information for new lots as normal.

Dependent on the configuration, the valuation on any 100% checked items may be automatically recalculated based on new budget figures.

Purchase Orders

Orders for specific lots

A lot can be deleted provided that the orders were not created from BQ as these are linked to the costing section which will not be deleted. **

New lots can be added as new lines on change orders to existing orders provided these were not created from BQ.

If not raised from BQ, any order change orders will need to be calculated manually and input in the normal way.

Job Status

Lot Costing

Deletion of a lot will not delete the costing section for the lot if there are any costs on it.

Lot costings for new lots from all sources as normal.

Existing cost transactions are unaffected and costs can continue to be posted as normal.

customer care

Calls

A lot cannot be deleted if there is a call recorded against it. **

Input all information for new lots as normal.

customer care is unaffected by template changes.

* Note that Coins ERP+ Land Management stores the lists of templates and lots against each appraisal and Coins ERP+forecast stores the list of lots against each forecast, so these modules are unaffected by development re-plans - each appraisal/forecast will reflect the site plan as it was recorded at the time.

** If a lot cannot be deleted then it can be changed to "non-sellable" and any costs and other information can be manually transferred/cancelled/deleted as appropriate.

*** A lot can change template at any time (a warning message will be displayed once VAP budgets exists, but this can be overridden.)