The purpose of this document is to outline how to add date triggers and update the existing assets through the configurable asset load

  1. Go to Fixed Assets>Setup>Maintenance>Asset Trigger Definitions.

    Figure 1: Asset Trigger Definition

  2. Click ADD.

  3. Fill in the appropriate fields.

    Figure 2: Add Trigger Definition

    • Trigger- the name of the trigger being added

    • Description- brief description of the trigger

    • Data Type- the type of data the trigger represents. In this case, it is Date

    • Format- the progress display format to be used for the trigger

    • Trigger Type- this combined with the Value determines how the expiration value for the trigger is reset

    • Value- the reset value, which determines what the expires field on the trigger is reset to. The entry in Trigger Type governs how the trigger is reset.

    • Main Trigger- this is used if the new trigger being added is a secondary trigger

    • Validation- how COINS responds when the trigger is triggered. The options are:

      None- no warning or error are given

      Warning- a warning message appears but gives the user the option to continue anyway (select the asset)

      Error- an error message appears and does not allow the user to continue (asset cannot be selected)

  4. Click SAVE.

  5. Go to Fixed Assets>Setup>Maintenance>Caption Maintenance

    Figure 3: Select/Add a Caption

  6. Select a caption that correctly corresponds to the trigger that was just added. If there is no option that corresponds accurately to the newly entered trigger ADD a new one.

    Figure 4: Select/Add a Caption

    • Code- Enter a code to identify the caption

    • Caption- the text that will be used as the prompt form the caption

    • Group- the caption group to be associated with this caption

    • Freq- how often the caption needs to be updated

  7. Click SAVE.

  8. Click the hyperlink for the appropriate caption.

    Figure 5: Select Hyperlink

  9. Go to the Trigger Tab and select ADD.

    Figure 6: Add Trigger

    Figure 7: Select Trigger

  10. Look up the trigger that was previously made to link it to the caption. Then click SAVE.

  11. Now the trigger will be linked with an asset group. Go to Go to Fixed Assets>Setup>Maintenance>Asset Groups

    Figure 8: Linking Trigger to an Asset Group

  12. Hyperlink onto the asset group that should be linked to the trigger.

    Figure 9: Opening Triggers Tab

  13. Go to the Triggers Tab and click OPEN.

    Figure 10: Selecting Trigger

  14. Select the appropriate trigger and click on the +. This will bring the selected trigger to the selected field on the right.

    Figure 11: Saving

  15. Once selected, click SAVE.